| Key Facts | |
|---|---|
| Client Name: | Lincoln City Council |
| Contract: | |
| Architect: | City of Lincoln Architectural Consultancy |
| Procurement: | Tender |
| Contract Period: | 26 Weeks |
| Project Status: | Project Completed |
Project Details
The was a major refurbishment of an existing Grade II heritage listed building to form an auditorium and entertainment complex including the design and construction of new main entrance area and substation.