USDA EMPP (Dalehead Food) Extension
Spalding
| Key Facts | |
|---|---|
| Client Name: | Dalehead Foods (Tulip Ltd) |
| Contract: | Traditional |
| Architect: | Peter Haddon and Partners |
| Procurement: | Tendered |
| Contract Period: | 32 weeks |
| Project Status: | Project Underway |
Project Details
The construction of two new amenity blocks to service the butchery and dirty slaughter elements of the existing abattoir. Both buildings are steel framed with feature cladding and curtain walling serviced with AC, ventilation and low energy lighting. We are also including photovoltaic panels and rainwater harvesting to reduce the environmental impact of the scheme. The project is due for completion in July 2012.